Attention please! Here is the shortcut to pass your ACT-VERBAL exam! Get yourself well prepared for the Admission Test ACT-VERBAL ACT-Verbal exam is really a hard job. But don’t worry! We, CertBus, provides the most update exam PDF and VCEs. With CertBus latest exam questions and answerss, you’ll pass the ACT-VERBAL ACT-Verbal exam in an easy way.

We CertBus has our own expert team. They selected and published the latest ACT-VERBAL preparation materials from Admission Test Official Exam-Center: http://www.certgod.com/ACT-Verbal.html

QUESTION NO:60

A customer is installing a new POWER7 server with IBM i as the host partition for three additional IBM i

partitions. The server has just one 4 port Ethernet card.

The administrator needs to achieve IP connectively for all four partitions.

What should the administrator do?

A. Purchase additional Ethernet cards for the client partitions.

B. Connect each partition to one of the ports on the 4 port Ethernet card.

C. On the hosting partition, create a bridge using one of the ports of the Ethernet card to a virtual Ethernet network. Connect each of the client partitions to the virtual Ethernet network.

D. Connect each partition to a virtual network.Configure IP on each client partition to use the host partition as an IP gateway.Add routes to the corporate router pointing to the host partition as the gateway to the client partitions.

Correct Answer: C

QUESTION NO:21

An IBM System Storage DS8700 is being installed at a global corporation’s headquarters location. The

storage must be available worldwide. A great deal of coordination is required to schedule this

implementation across the corporation. Who is best positioned to fill the role of implementation resource

coordinator?

A. IBM Service Support Representative

B. IBM Advanced Technical Support Representative

C.

IBM Field Technical Support Representative

D. IT Manager of the customer

Correct Answer: D

QUESTION NO:8

Companycom has a p5 595 running 12 LPARs. They are interested in high bandwidth, secure

communication between two of the LPARs within the p5 595 server. They do not have any

unused Ethernet adapters. Which of the following recommendations will best meet this

requirement?

A. Utilize the integrated 10/100/1000 network interface

B. Implement Virtual Ethernet to enable inter-partition communication

C. Implement shared Ethernet with the Ethernet adapters utilized in the other LPARs

D. Implement a Point to Point protocol serial communication between the p5 595 serial ports

Answer: B

QUESTION NO:69

Which is a benefit of using the IBM DS8000 FlashCopy SE (PTC-SE)?

A. FlashCopy SE (PTC-SE) is much faster than the traditional DS8000 full-volume FlashCopy

B. FlashCopy SE (PTC-SE) also supports background copy

C.

FlashCopy SE (PTC-SE) is optimized for use in cases where a high percentage of the source volume

is updated during the life of the relationship

D.

the additional capacity required forFlashCopy SE (PTC-SE) must only be planned for data which is

changed on the source volume during host I/O transaction

Correct Answer: D

QUESTION NO:43

The HMC software has just been upgraded remotely via the WebSM client. It now needs to be

rebooted to make the update active. How can this be accomplished?

A. Use ssh to connect to the HMC and reboot

B. The upgrade will display complete and ask you to reboot

C. Select shutdown in the Management section of the WebSM client

D. Once logged out of the WebSM client it will ask to logoff, shutdown or reboot. Select reboot.

Answer: A