All4Certs CompTIA Archive,Exam Archive CertBus CompTIA PK0-004 the Most Up to Date VCE And PDF Instant Download

CertBus CompTIA PK0-004 the Most Up to Date VCE And PDF Instant Download

CertBus 2021 Real CompTIA PK0-004 CompTIA Project Exam VCE and PDF Dumps for Free Download!

PK0-004 CompTIA Project Exam PDF and VCE Dumps : 505QAs Instant Download: https://www.certgod.com/pk0-004.html [100% PK0-004 Exam Pass Guaranteed or Money Refund!!]
☆ Free view online pdf on CertBus free test PK0-004 PDF: https://www.certgod.com/online-pdf/pk0-004.pdf

Following PK0-004 505QAs are all new published by CompTIA Official Exam Center

You can prepare for your CompTIA CompTIA Project Newest PK0-004 QAs exam with less time and effort because we,CertBus, will act as your reliable guide to pass your CompTIA CompTIA Project Latest PK0-004 pdf dumps exam. Our CompTIA CompTIA Project Newest PK0-004 vce exam dumps are the latest and with the most accurate answers. We offer CompTIA CompTIA Project Latest PK0-004 free download PDF dumps and CompTIA CompTIA Project Apr 10,2021 Latest PK0-004 pdf VCE. Both are the most effective version.

CertBus – pass all PK0-004 certification exams easily with our real exam practice. latest update and experts revised. CertBus it exam study material and real exam questions and answers help you pass PK0-004 exams and get PK0-004 certifications easily. get PK0-004 certification with CertBus study materials and practice tests.

We CertBus has our own expert team. They selected and published the latest PK0-004 preparation materials from CompTIA Official Exam-Center: https://www.certgod.com/pk0-004.html

Question 1:

A milestone task on the critical path has been completed.

Which of the following should the project manager notify?

A. Owner of predecessor task

B. Project team

C. Project sponsor

D. Project steering committee

Correct Answer: C


Question 2:

Team members have reported poor sound quality during critical, time-sensitive conference calls. Which of the following may be a more effective means of communication?

A. One-on-one meetings

B. Project wiki

C. Text messages

D. Social media

Correct Answer: A


Question 3:

A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early.

Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

A. Cost

B. Predecessors

C. Lag

D. Durations

E. Resource loading

F. Subtasks

G. Float

Correct Answer: AE


Question 4:

A project team has determined it will need to source data from a system that was not part of the project scope.

The role of the project manager is to analyze which of the following impacts?

A. Technical design, schedule, and budget

B. Business process impacts and resourcing

C. New software and hardware requirements

D. Schedule, budget, and quality

Correct Answer: C


Question 5:

An organization has multiple projects that are taking place simultaneously.

Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

A. PMO

B. Project sponsor

C. Project coordinator

D. HR

Correct Answer: B

References: Kim Heldman, CompTIA Project Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82


PK0-004 VCE DumpsPK0-004 Study GuidePK0-004 Exam Questions

Question 6:

A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?

A. Team Building

B. Team Selection

C. Resource loading

D. Resource leveling

Correct Answer: A


Question 7:

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?

A. Personal preference

B. Intra-organizational differences

C. Culture

D. Time zone

Correct Answer: D


Question 8:

A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?

A. Issue log

B. Status report

C. Risk register

D. SOW

Correct Answer: B


Question 9:

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

A. Revise the project plan.

B. Update the issue log.

C. Request additional funding.

D. Issue a change request.

Correct Answer: A


Question 10:

A project is in the initiation phase. Which of the following tasks will take place during this phase?

A. Develop a WBS.

B. Define the project requirements.

C. Create a project charter.

D. Acquire the project resources.

Correct Answer: C


CertBus exam braindumps are pass guaranteed. We guarantee your pass for the PK0-004 exam successfully with our CompTIA materials. CertBus CompTIA Project exam PDF and VCE are the latest and most accurate. We have the best CompTIA in our team to make sure CertBus CompTIA Project exam questions and answers are the most valid. CertBus exam CompTIA Project exam dumps will help you to be the CompTIA specialist, clear your PK0-004 exam and get the final success.

PK0-004 CompTIA exam dumps (100% Pass Guaranteed) from CertBus: https://www.certgod.com/pk0-004.html [100% Exam Pass Guaranteed]

Why select/choose CertBus?

Millions of interested professionals can touch the destination of success in exams by certgod.com. products which would be available, affordable, updated and of really best quality to overcome the difficulties of any course outlines. Questions and Answers material is updated in highly outclass manner on regular basis and material is released periodically and is available in testing centers with whom we are maintaining our relationship to get latest material.

BrandCertbusTestkingPass4sureActualtestsOthers
Price$45.99$124.99$125.99$189$69.99-99.99
Up-to-Date Dumps
Free 365 Days Update
Real Questions
Printable PDF
Test Engine
One Time Purchase
Instant Download
Unlimited Install
100% Pass Guarantee
100% Money Back
Secure Payment
Privacy Protection

Leave a Reply

Your email address will not be published. Required fields are marked *