One of my colleague recommend me that CertBus Project PK0-003 dumps are effective and helpful. Thank goodness I followed up with him and choose CertBus as my assistance on my Project PK0-003 Project (2009) certification exam! I passed my CompTIA Project PK0-003 exam very easily. I was lucky, all my questions in the exams were from my CompTIA Project PK0-003 dumps.
We CertBus has our own expert team. They selected and published the latest PK0-003 preparation materials from CompTIA Official Exam-Center: http://www.certgod.com/PK0-003.html
QUESTION NO: 4
Which of the following is used to provide a functional description of the efforts which are
required in order to accomplish a task?
A. Gantt chart
B. PERT
C. GERT
D. WBS dictionary
Answer: D
QUESTION NO: 11
A new software solution is being deployed. The customer realizes that an important piece
of the software must be purchased in order for the project to be successful. Which of the
following is TRUE about this scenario?
A. The new piece of software will most likely expand the scope of the project therefore a
new scope statement must be written.
B. The current project must be completed and a new project can be started to implement
the additional software.
C. Quality management metrics are affected therefore the project manager should review
the quality of the project.
D. Project schedule may be affected and the project manager must follow the change
control process.
Answer: D
5
QUESTION NO: 5
A project manager is entering the list of a project’s activities with their estimated begin and
end time to visualize which activities overlap and when the project is scheduled to end.
Which of the following is the project manager building?
A. Gantt chart
B. Work Breakdown Structure
C. Critical Path
D. PERT chart
Answer: A
QUESTION NO: 6
The project manager is sequencing a set of activities. They discover that some of the
activities may or may not occur based on the outcome of other activities. Which of the
following is BEST suited in this situation to show the activities’ logical relationship?
A. Gantt
B. ADM
3
C. CCB
D. CCM
Answer: B
QUESTION NO: 7
Which of the following is the MAIN difference between bottom up and top down cost
estimation?
A. Bottom up leads to a more accurate cost estimate than top down because it is
performed by subject matter experts
B. Top down leads to a more accurate cost estimate because it is performed by upper
management with direct access to budget information
C. Bottom up leads to a less accurate cost estimate because it is breaks down the task into
smaller subtasks where some tasks may not have a cost
D. Both top down and bottom up are equally accurate estimation of a project’s total cost
because they both refer to resources assigned by the project sponsor
Answer: A
QUESTION NO: 12
While performing a scheduled walkthrough at a construction site, the customer points out a
discrepancy. Which of the following is the FIRST step that should be taken before
submitting a change control form?
A. Consult the project sponsor
B. Identify the change
C. Perform a feasibility study
D. Perform impact analysis
Answer: B
QUESTION NO: 1
Which of the following MUST be clearly defined in a project charter?
A. Quality
B. Scope
C. Action items
D. WBS
Answer: B
QUESTION NO: 10
After the ground breaking at a new construction site, the pile driving operation comes to a
full stop due to the nature of the terrain. Which of the following is MOST likely to occur?
A. The project communication plan must be updated and a stakeholder meeting must be
scheduled.
B. The project manager must manage the new issue as the project schedule could be
delayed.
C. The project manager must implement conflict resolution and review the resource
requirement.
D. The project scope statement must be reviewed and the project manager must prepare a
performance report.
Answer: B
QUESTION NO: 9
One of the MAIN purposes of a kick-off meeting is to:
4
A. Assign and review roles and responsibilities to the project team.
B. Allow the project sponsor to introduce the project manager to the team.
C. Review the project definition document and make the appropriate changes.
D. Ensure project team members communicate amongst each others.
Answer: A
QUESTION NO: 13
A project team member has identified a required change to one of their assigned tasks.
The change would alter the order in which other tasks must be completed. Which of the
following should be done NEXT?
A. Implement the change
B. Update the change registry
C. Document the change
D. Perform an impact analysis
Answer: D
CertBus exam braindumps are pass guaranteed. We guarantee your pass for the PK0-003 exam successfully with our CompTIA materials. CertBus Project (2009) exam PDF and VCE are the latest and most accurate. We have the best CompTIA in our team to make sure CertBus Project (2009) exam questions and answers are the most valid. CertBus exam Project (2009) exam dumps will help you to be the CompTIA specialist, clear your PK0-003 exam and get the final success.
PK0-003 Latest questions and answers on Google Drive(100% Free Download): https://drive.google.com/file/d/0B_3QX8HGRR1mV1VVRWVhb3B2b2s/view?usp=sharing
PK0-003 CompTIA exam dumps (100% Pass Guaranteed) from CertBus: http://www.certgod.com/PK0-003.html [100% Exam Pass Guaranteed]
Why select/choose CertBus?
Millions of interested professionals can touch the destination of success in exams by certgod.com. products which would be available, affordable, updated and of really best quality to overcome the difficulties of any course outlines. Questions and Answers material is updated in highly outclass manner on regular basis and material is released periodically and is available in testing centers with whom we are maintaining our relationship to get latest material.