Don’t worry about how to get yourself well prepared your PMI Certification PMI-001 exam! CertBus will work you out of your PMI Certification PMI-001 exam with the latest updated PMI-001 Project Management Professional PDF and VCE dumps. CertBus provides the latest real PMI PMI Certification PMI-001 exam preparation material, covering every aspect of PMI-001 exam curriculum.
We CertBus has our own expert team. They selected and published the latest PMI-001 preparation materials from PMI Official Exam-Center: http://www.certgod.com/PMI-001.html
QUESTION NO: 3
You plan to hold a series of meeting as you execute the project plan. While different attendees will
attend each meeting, a best practice to follow is to:
A. Group stakeholders into categories to determine which ones should attend each meeting
B. Not mix the types of meetings on your project
C. Be sensitive to the fact that stakeholders often have very different objectives and invite them to
determine the meeting’s agenda
D. Recognize that roles and responsibilities may overlap so focus on holding meetings primarily
for decision making
Answer: B
Explanation:
Meetings are a tool and technique used in direct and manage project work. Meetings tend to be
one of three types: information exchange; brainstorming, option evaluation, or design; or decision
making. A best practice is to not combine the types of meetings and prepare for them with a well-
defined agenda, purpose, objective, and time frame. They should be documented using minutes
and action items. [Executing]
QUESTION NO: 6
When you established the change control board for your avionics project, you established specific
procedures to govern its operation. The procedures require all approved changes to baselines to
be reflected in the______________.
A. Performance measurement baseline
B. Change management plan
C. Quality assurance plan
D. Project management plan
Answer: D
Explanation:
The project management plan must be updated changes to subsidiary plans and baselines subject
4
to formal change control processes. Those changes must be communicated to appropriate
stakeholders in a timely manner. [Monitoring and Controlling]
QUESTION NO: 12
You are fairly new to managing a project but have been a team member for many years. You are
pleased you were selected to manage your company’s 2015 model line of hybrid vehicles. You are
now planning your project and have been preparing the subsidiary plans as well. You realize some
project documents also are required to help manage your project. An example of one that you
believe will be especial helpful is the______________.
A. Business case
B. Key performance indicators
C. Project management information system
D. Project statement of work
Answer: D
Explanation:
The project statement of work is a useful document as it describes the products, services, or
results the project is to deliver. It references the business need, product scope description, and the
strategic plan. [Initiating and Planning]
7
PMI®, PMBOK® Guide, 2013, 68, 78
QUESTION NO: 13
You work for a telecommunications company, and when developing a project management plan
for a new project, you found that you must tailor some company processes because the product is
so different than those products typically produced by your company. To tailor these processes,
you will follow______________.
A. Standardized guidelines and work instructions
B. Stakeholder risk tolerances
C. Expert judgment
D. Structure of your company
Answer: A
Explanation:
Standardized guidelines and work instructions are an organizational process asset to consider as
the project management plan is developed. They include guidelines and criteria to tailor the
organization’s set of standard processes to satisfy the specific needs of the project. [Planning]
PMI®, PMBOK® Guide, 2013, 75
QUESTION NO: 7
You are beginning a new project staffed with a virtual team located across five countries. To help
avoid conflict in work priorities among your team members and their functional managers, you ask
the project sponsor to prepare a______________.
A. Memo to team members informing them that they work for you now
B. Project charter
C. Memo to the functional managers informing them that you have authority to direct their
employees
D. Human resource management plan
Answer: B
Explanation:
Although the project charter cannot stop conflicts from arising, it can provide a framework to help
resolve them, because it describes the project manager’s authority to apply organizational
resources to project activities. [Initiating]
QUESTION NO: 9
Facilitation techniques are used throughout project management. Your company is embarking on
a project to completely eliminate defects in its products. You are the project manager for this
project, and you are developing your project charter. To assist you, which of the following
facilitation techniques did you use?
A. Surveys
B. Delphi approach
C. Meeting management
D. Focus groups
Answer: C
Explanation:
Meeting management is an example of a facilitation technique used in developing the project
charter as meetings may be held with key stakeholders and subject matter experts. Other
facilitation techniques used to guide preparation of the charter are brainstorming, problem solving,
and conflict resolution. [Initiating]
QUESTION NO: 4
You are the project manager in charge of developing a new shipping container for Globus Ocean
Transport, which needs to withstand winds of 90 knots and swells of 30 meters. In determining the
dimension of the container and the materials to be used in its fabrication, you convene a group of
knowledgeable professionals to gather initial requirements, which will be included in
the______________.
A. Project charter
B. Bill of materials
C. WBS
D. Project Statement of Work
Answer: A
3
Explanation:
The project charter documents the business needs, assumptions, constraints, understanding of
the customer needs and high-level requirements and what the new product, service, or result is to
satisfy. It is the document used to formally authorize the project. [Initiating]
QUESTION NO: 2
You are managing a large project with 20 key internal stakeholders, eight contractors, and six
team leaders. You must devote attention to effective integrated change control. This means you
are concerned primarily with______________.
A. Reviewing, approving, and controlling changes
B. Maintaining baseline integrity, integrating product and project scope, and coordinating change
across knowledge areas
C. Integrating deliverables from different functional specialties on the project
D. Establishing a change control board that oversees the overall project changes
Answer: A
Explanation:
Performing integrated change control consists of coordinating and managing changes across the
project. Activities that occur within the context of perform integrated change control include:
validate scope, control scope, control schedule, control costs, perform quality assurance, control
2
quality, manage the project team, control communications, control risks, conduct procurements,
control procurements, manage stakeholder engagement, and control stakeholder engagement.
[Monitoring and Controlling]
QUESTION NO: 10
The direct and manage project work process truly is important in project management. It affects
many other key processes and uses inputs from others. Working with your team at its kickoff
meeting, you explain the key benefit of this process is to______________.
A. Implement approved changes
B. Provide overall management of the project work
C. Lead and perform activities in the project management plan
D. Perform activities to accomplish project objectives
Answer: B
Explanation:
While all of the answers apply to the direct and manage project work process, the key benefit is
that it involves providing overall management of the work of the project, encompassing the other
answers listed. [Executing]
6
QUESTION NO: 8
The purpose of economic value added (EVA) is to______________.
A. Determine the opportunity costs associated with the project
B. Determine a non–time-dependent measure of profit or return
C. Assess the net operating profit after taxes
D. Evaluate the return on capital percent versus the cost of capital percent
Answer: D
Explanation:
Evaluate the return on capital percent versus the cost of capital percent
EVA quantifies the value a company provides to its investors and seeks to determine if a company
is creating or destroying value to its shareholders. It is calculated by subtracting the expected
return, (represented by the capital charge), from the actual return that a company generates,
(represented by net operating profit after taxes). [Initiating]
5
CertBus exam braindumps are pass guaranteed. We guarantee your pass for the PMI-001 exam successfully with our PMI materials. CertBus Project Management Professional exam PDF and VCE are the latest and most accurate. We have the best PMI in our team to make sure CertBus Project Management Professional exam questions and answers are the most valid. CertBus exam Project Management Professional exam dumps will help you to be the PMI specialist, clear your PMI-001 exam and get the final success.
PMI-001 Latest questions and answers on Google Drive(100% Free Download): https://drive.google.com/file/d/0B_3QX8HGRR1mb2dxdmRsOEFGZ0k/view?usp=sharing
PMI-001 PMI exam dumps (100% Pass Guaranteed) from CertBus: http://www.certgod.com/PMI-001.html [100% Exam Pass Guaranteed]
Why select/choose CertBus?
Millions of interested professionals can touch the destination of success in exams by certgod.com. products which would be available, affordable, updated and of really best quality to overcome the difficulties of any course outlines. Questions and Answers material is updated in highly outclass manner on regular basis and material is released periodically and is available in testing centers with whom we are maintaining our relationship to get latest material.